基于 FAHP-BN 的军队工程代建模式风险评估方法()

《工程管理学报》[ISSN:/CN:]

期数:
2017年04期
页码:
99-104
栏目:
项目管理
出版日期:
2017-08-20

文章信息/Info

Title:
The Risk Assessment Method of Agent Construction Mode in MilitaryProject Based on FAHP and Bayesian Network
文章编号/Paper ID:
1674-8859(2017)04-099-06
作者:
包泽蓉 马志明 辜文杰 刘宪庆
1. 解放军后勤工程学院 管理科学与工程系;2,3,4. 解放军后勤工程学院 军事工程管理系
Author(s):
BAO Ze-rong MA Zhi-ming GU Wen-jie LIU Xian-qing
1. Dept. of Management Science and Engineering,Logistical Engineering University of PLA;2,3,4.Dept. of Military Engineering Management,Logistical Engineering University of PLA
关键词:
模糊层次分析法贝叶斯网络代建模式风险评估
Keywords:
fuzzy analytic hierarchy processbayesian networkagent construction moderisk assessment
DOI:
10.13991/j.cnki.jem.2017.04.018
摘要:
为解决军队工程代建模式风险评估过程中的主观性与不确定性,提出一种模糊层次分析法与贝叶斯网络相结合的风险评估方法。以军队代建工程质量安全事故数据为基础,建立模糊层次分析模型对代建工程风险损失权重进行评估。构建贝叶斯网络,利用 Netica 软件推理风险事件发生概率。结合风险等级隶属函数,得出代建工程整体风险等级。该方法可以有效降低风险评估的主观因素,及时发现高风险节点,更准确地把握风险态势。实例评估结果与工程实际相符,验证了评估方法的合理性和适用性,对工程代建模式风险评估具有一定的参考价值。
Abstract:
In order to solve the subjectivity and uncertainty in the risk assessment of the agent construction in military,a riskassessment method of project in agent construction mode that combines fuzzy analytic hierarchy process and Bayesian network hasbeen proposed. On the basis of the statistics of safety incidents of military agent construction,the loss weight of agent construction isassessed by FAHP method. Bayesian network is built and Netica software is used to deduce the probability of risk incidents.Combined with the membership function of risk level,the risk rank of the whole agent construction is concluded. This method can beused to efficiently lower the subjective elements of risk assessment,find high risk node immediately and more correctly grasp therisk situation. The conformation between the assessment outcome of example and actual project has verified the rationality andfeasibility of the assessment method,which has a certain reference value for the risk assessment of agent construction mode.

中图分类号/Chinese Library Classification:

F283

文献标识码/Document Code:

A

参考文献/References

备注/Memo

备注/Memo:
收稿日期:2017-02-23.
基金项目:
重庆市建设科技计划项目(城科字 2014 年 09-2 号).
作者简介:
包泽蓉(1992-),通讯作者,男,硕士研究生,研究方向:军队工程项目风险管理;
马志明(1964-),男,教授,研究生导师,研究方向:军事工程管理,军队营房建设;
辜文杰(1976-),男,副教授,研究方向:军事工程施工与管理;
刘宪庆(1986-),男,博士,讲师,研究方向:军事工程施工与管理。
更新日期/Last Update: